Decision Panel

The Decision Panel scores and ranks your project's milestones by risk, helping you decide where to focus. It uses a 7-layer analysis engine that combines critical path data, dependency graphs, progress trajectories, and blocker status to produce actionable recommendations.

Accessing the Decision Panel

  1. Click the Schedule ribbon tab.
  2. Click the Decision Panel button.

Milestone Tiers

Each milestone is classified into a risk tier based on the combined scoring:

TierColourMeaning
BlockerRedMilestone is blocked — one or more predecessors have unresolved blockers or critical-path violations
CriticalOrangeHigh probability of missing the milestone date without intervention
HighAmberSignificant risk — schedule slippage or cost overrun detected in the dependency chain
MediumYellowModerate risk — some predecessor tasks are behind but recovery is feasible
WatchBlueMinor variance — worth monitoring but no action needed yet
DoneGreenMilestone already completed

The 7-Layer Scoring Engine

The Decision Panel analyses each milestone through these layers in sequence:

  1. Graph Validation — checks for dependency cycles and orphaned milestones
  2. Topological Sort — orders milestones by dependency chain depth
  3. Critical Path — identifies which milestones sit on the critical path
  4. Milestone Scoring — combines delay days, blocker count, velocity trend, and cost variance into a composite score
  5. Ranking — sorts milestones by composite score and assigns tiers
  6. Recovery Advisor — generates recommended actions for at-risk milestones
  7. UI Rendering — presents the ranked list with drill-down detail

Recovery Advisor

For milestones in the Blocker, Critical, or High tiers, the panel generates recovery actions ranked by impact and effort:

Trajectory Modes

The panel offers three forecast modes that adjust how optimistically it projects future progress:

ModeWeightWhen to use
Conservative0.5×Team has a history of slipping — assume slower progress
Balanced1.0×Default — uses current velocity as-is
Aggressive2.0×Team is accelerating or extra resources have been added
The Decision Panel updates in real time as you change task progress, dates, or dependencies. You don't need to manually refresh it.