The EVM report measures cost efficiency and schedule efficiency using three data points: how much work was planned (PV), how much has been completed (EV), and how much has been spent (AC). From these three numbers, DPlan derives the full suite of EVMS metrics used by professional project managers.
| Input | Name | How DPlan calculates it |
|---|---|---|
| BAC | Budget at Completion | Sum of all task costs in the project. Fully automatic. |
| PV | Planned Value | Budgeted cost of work scheduled up to today. Uses uniform cost distribution (same as Cash Flow). Fully automatic. |
| EV | Earned Value | Σ (task budget × task % complete). Uses the progress % you enter on each task. Automatic once you set progress. |
| AC | Actual Cost | Σ of Actual Cost ($) fields entered manually on tasks. You must enter this — it is not calculated. |
| Metric | Formula | What it means | Good value |
|---|---|---|---|
| CV — Cost Variance | EV − AC | Are we over or under budget for the work done? | Positive (EV > AC) |
| SV — Schedule Variance | EV − PV | Are we ahead or behind plan in terms of earned value? | Positive (EV > PV) |
| CPI — Cost Performance Index | EV ÷ AC | How many dollars of value do we get for each dollar spent? | >= 1.0 |
| SPI — Schedule Performance Index | EV ÷ PV | How efficiently are we earning value relative to plan? | >= 1.0 |
| EAC — Estimate at Completion | BAC ÷ CPI | Forecast of total cost at completion, assuming current efficiency continues. | Close to BAC |
| ETC — Estimate to Complete | EAC − AC | How much more money do we need to finish the project? | As low as possible |
| VAC — Variance at Completion | BAC − EAC | Will we finish over or under budget? | Positive (under budget) |
| TCPI — To-Complete Performance Index | (BAC − EV) ÷ (BAC − AC) | The CPI efficiency you must maintain for remaining work to finish on budget. | <= 1.0 (achievable) |
| Value | Meaning | Colour in DPlan |
|---|---|---|
| >= 1.0 | Under budget / ahead of schedule | Green ✓ |
| 0.9 – 1.0 | Slightly over / slightly behind — monitor closely | Amber ⚠ |
| < 0.9 | Significantly over budget / behind schedule — corrective action needed | Red ✗ |
The Per-Task Earned Value table shows EV and AC for each costed task. The Cost Var. (CV) column highlights individual tasks in green (under budget) or red (over budget). Sort by the most negative CV to find your biggest cost problems.
Project: Waterfront Office Complex — 40% complete by schedule BAC = $1,800,000 (total project budget) PV = $720,000 (planned spend to date, 40% × BAC with uniform distribution) EV = $648,000 (36% complete × BAC — slightly behind schedule) AC = $720,000 (what was actually spent — same as PV) CV = EV − AC = $648,000 − $720,000 = −$72,000 ← OVER BUDGET SV = EV − PV = $648,000 − $720,000 = −$72,000 ← BEHIND SCHEDULE CPI = EV / AC = 0.90 ← On the amber threshold SPI = EV / PV = 0.90 ← Behind schedule EAC = BAC / CPI = $2,000,000 ← 11% over budget at completion VAC = BAC − EAC = −$200,000 ← Forecast overrun TCPI = (1,800,000 − 648,000) / (1,800,000 − 720,000) = 1.067 ← Needs better performance
This project needs corrective action — either reduce scope, add resources, or re-baseline with client approval.