Progress Forecast

The Progress Forecast uses Earned Value metrics (SPI and CPI) to project when your project will actually finish and what it will actually cost — based on current performance, not the original plan.

Accessing the Forecast

  1. Dashboard — the forecast mini-card shows a summary with a link to the full report.
  2. Reports tab → select Progress Forecast in the sidebar.

Key Metrics

MetricFormulaWhat it tells you
SPIEV / PVSchedule efficiency. SPI = 1.0 means on schedule. Below 1.0 = behind.
CPIEV / ACCost efficiency. CPI = 1.0 means on budget. Below 1.0 = over budget.
EACBAC / CPIEstimate at Completion — projected total cost based on current spending rate.
ETCEAC − ACEstimate to Complete — how much more you'll need to spend.
Projected FinishRemaining duration / SPIWhen the project will actually end at the current pace.

Three Scenarios

The forecast report shows three projections side by side:

ScenarioAssumption
Best CasePerformance improves — SPI and CPI capped at 1.0 (on-plan pace)
LikelyCurrent SPI and CPI continue as-is
Worst CasePerformance degrades further — SPI and CPI reduced by 0.2

Timeline Visualisation

The forecast includes a timeline bar showing:

Schedule Variance

The report shows the schedule variance in days — positive means ahead of schedule, negative means behind. For example:

The forecast needs task dates and progress to work. Cost forecasts (EAC, ETC) additionally require actual cost entries on tasks — without them, only schedule forecasts are shown.

Dashboard Mini-Card

The Dashboard shows a compact forecast summary card with: